Updated 11/17/17 

Week of 11/19 to 11/25
No line or drill work expected this week.

Week of 11/26 to 12/2
Crews will remove old wire from right-of-way off of Bailey Road to Wheeler Road.

Week of 12/3 to 12/9
Crews will install structure and transfer wire on right-of-way off of Broadway Road.
Crews will install remaining bail steps and clean out old wire.
Crews will sag, clip and space wire from Wheeler Road to the New Hampshire state line.