Updated 9/22/17 

Week of 9/24 to 9/30
Crews will start pulling wire between the Merrimack River and Wheeler Road.
Crews will set structures between Andover Street and Methuen Street.

Week of 10/1 to 10/7
Crews will finish wire work between the Merrimack River and Wheeler Road.
Crews will finish setting structures between Andover Street and Methuen Street.

Week of 10/8 to 10/14
Crews will set up and start pulling wire from Andover Street to the Merrimack River.