Eversource Portion

The northern portion of the MVRP in Hudson will be constructed by Eversource, and the southern portion will be constructed by National Grid.

Updated 11/17/17

Week of 11/13 to 11/18

No planned work activities

Week of 11/20 to 11/24*

*No work on Thursday, November 23 in Observance of Thanksgiving  

No planned work activities

Week of 11/27 to 12/2

No planned work activities

 

National Grid Portion

Updated 11/17/17

Week of 11/19 to 11/25
Crews will begin cutover work and pulling wire on right-of-way off of Griffin Road to the National Grid-Eversource split.

*No work on Thursday, November 23rd in Observance of Thanksgiving  

Week of 11/26 to 12/2
No line or drill work expected this week.

Week of 12/3 to 12/9
No line or drill work expected this week.