Andover, MA

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization

Dracut, MA

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization

 

Tewksbury, MA

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization

Hudson, NH

Eversource Portion

The northern portion of the MVRP in Hudson will be constructed by Eversource, and the southern portion will be constructed by National Grid.

Updated 12/11/17

Week of 12/10 - 12/16

Punch list items, restoration, and demobilization

Week of 12/17 - 12/23

Punch list items, restoration, and demobilization

Week of 12/24 - 12/30

Punch list items, restoration, and demobilization

 

National Grid Portion

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization

Londonderry, NH

Updated 12/11/17 

Week of 12/10 - 12/16

Punch list items, restoration*, and demobilization

Week of 12/17 - 12/23

Punch list items, restoration*, and demobilization

Week of 12/24 - 12/30

Punch list items, restoration*, and demobilization

*Restoration is weather permitting. Any remaining restoration work will take place in Spring 2018.

Pelham, NH

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization

Windham, NH

Updated 12/15/17

Week of 12/17 to 12/23

Start demobilization and work on punch list items

Week of 12/24 to 12/30

Demobilization