Andover, MA

Updated 11/17/17

Week of 11/19 to 11/25
Crews will start wire pull at I-495.

Week of 11/26 to 12/2
Crews will finish wire pull at I-495.

Week of 12/3 to 12/9
No line or drill work expected this week.

Dracut, MA

Updated 11/17/17 

Week of 11/19 to 11/25
No line or drill work expected this week.

Week of 11/26 to 12/2
Crews will remove old wire from right-of-way off of Bailey Road to Wheeler Road.

Week of 12/3 to 12/9
Crews will install structure and transfer wire on right-of-way off of Broadway Road.
Crews will install remaining bail steps and clean out old wire.
Crews will sag, clip and space wire from Wheeler Road to the New Hampshire state line.

Tewksbury, MA

Updated 11/17/17

Week of 11/19 to 11/25
No line or drill work expected this week.

Week of 11/26 to 12/2
Crews will remove old wire from right-of-way off of Bailey Road to Wheeler Road.

Week of 12/3 to 12/9
No line or drill work expected this week.

Hudson, NH

Eversource Portion

The northern portion of the MVRP in Hudson will be constructed by Eversource, and the southern portion will be constructed by National Grid.

Updated 11/17/17

Week of 11/13 to 11/18

No planned work activities

Week of 11/20 to 11/24*

*No work on Thursday, November 23 in Observance of Thanksgiving  

No planned work activities

Week of 11/27 to 12/2

No planned work activities

 

National Grid Portion

Updated 11/17/17

Week of 11/19 to 11/25
Crews will begin cutover work and pulling wire on right-of-way off of Griffin Road to the National Grid-Eversource split.

*No work on Thursday, November 23rd in Observance of Thanksgiving  

Week of 11/26 to 12/2
No line or drill work expected this week.

Week of 12/3 to 12/9
No line or drill work expected this week.

Londonderry, NH

Updated 11/17/17 

Week of 11/13 to 11/18

Rt. 28 to Brewster Road: Wire installation activities

Wiley Hill to Elwood: Restoration activities.

Week of 11/20 to 11/24*

*No work on Thursday, November 23rd in Observance of Thanksgiving  

Rt. 28 to Brewster Road: Wire installation activities and clean up.

Elwood to Dan Hill: Restoration activities

Week of 11/27 to 12/2

Elwood to Dan Hill: Restoration activities

Pelham, NH

Updated 11/17/17

Week of 11/19 to 11/25
No line or drill work expected this week.

Week of 11/26 to 12/2
No line or drill work expected this week.

Week of 12/3 to 12/9
No line or drill work expected this week.

 

Windham, NH

Updated 11/17/17

Week of 11/19 to 11/25
No line or drill work expected this week.

Week of 11/26 to 12/2
No line or drill work expected this week.

Week of 12/3 to 12/9
No line or drill work expected this week.